Cardiff Road Construction Project

Project Information

06/09/2026

UPDATE (7/1/2026)

Monday July 6 – Friday July 16th

String line and curb prep will begin on Cardiff Road, Cardiff Circle, Twin Lake Circle, the South half of Solitude Drive, Biscayne Drive and Oakview circle.

We will also begin storm drain installation on Lake Mary Drive and North half of Solitude Drive.

Sidewalk removal will take place on Thursday and Friday, July 9th and 10th.

Concrete curb installation will start on the West end of Cardiff continuing through Cardiff Circle, Twin Lake Circle, and the South end of Solitude Drive.

Please have your vehicle removed and parked at a remote location during construction hours. You will not have access in and out of your driveways during this time frame. Work hours are 7AM-6:30PM.

Suggested parking locations are the LDS Church on Bengal Blvd, Dell Road and Brighton Way.

 

Cardiff Road Reconstruction Project Beginning Monday, June 8, 2026, Miller Paving Inc. will begin roadway and utility improvement work in the Cardiff Drive, Cardiff Circle, Twin Lake Circle, Solitude Drive, the Lake Mary Drive intersection, Oakview Circle, and Biscayne Drive areas.

Beginning Monday, June 8, 2026, Miller Paving Inc. will begin roadway and utility improvement work in the Cardiff Drive, Cardiff Circle, Twin Lake Circle, Solitude Drive, the Lake Mary Drive intersection, Oakview Circle, and Biscayne Drive areas.

Work will include concrete driveway approaches, curb and gutter, limited sidewalk replacement, raising and lowering manholes, storm drain upgrades, street light improvements, fire hydrant replacement, and roadway removal and replacement.

Miller Paving will coordinate with residents as work moves from area to area. Residents will be notified ahead of time when work is scheduled near their property.

When driveway approaches and/or curb and gutter are removed, driveway access will be unavailable during the concrete curing period. The curing period is approximately 7 days.

To help complete the work safely and efficiently, all vehicles must be removed from the work area between 7:00 AM and 5:30 PM, unless alternate arrangements have been made with Miller Paving. Please plan accordingly to avoid disruptions.

The project is scheduled to begin June 8, 2026, with tentative completion by September 7, 2026.

Questions or special arrangements may be directed to:

Miller Paving Inc.
Project Manager: Aaron Spackman
Phone: 801-618-7495

Cardiff Road, Cottonwood Heights, UT, USA